Claims / Construction contractor

How do I claim variations after the job is finished?

Updated

Start with the deadlines. Every Australian state and territory has security of payment law, and each sets its own time limit for a payment claim, so check the law for your site. For example, under Queensland's BIF Act 2017 a claim must usually be made within 6 months of the work, or within the contract time if that is shorter. Check the contract notice rules too.

How it flows

How do I claim variations after the job is finished?1. Check claim deadlines2. Gather and read all files3. Build the change timeline4. Price and send the claim

Gather the contract, drawings, programme, emails, diaries and cost records. Build a timeline of what changed and when.

Price each change from timesheets, invoices and subcontractor accounts. Be open about which costs are proven and which are estimated.

Send one claim with a register of changes and an index of proof. If it is refused, the same file supports adjudication.

Queensland example from the Building Industry Fairness (Security of Payment) Act 2017 (Qld). Other states and territories have their own Acts.

Rebuild the job from your files, list every change, price each one and send a claim within the contract and legal time limits. Do it quickly, because deadlines and memories both fade.

Need help with a claim?

Going to the home page in 2:00